The connection in Hobart is a significantly different kind of connection. It's a much smaller pipeline and a much smaller fee.

The board felt that with the two connections being virtually identical, they ought to have the same price. They approved the fee of $28,000 based on the similarity of the connection in Francis Creek. The authority is prepared to absorb the difference.

There were two different contractors, two different projects and they bid different prices to do the same amount of work.